Completed

Design, Fabrication and Installation of Piping for a Deaerator Pressure Vessel

Download Project

Client

Rio Tinto

Location

Gladstone, QLD

Completion Date

2018

Overview

Pructon was engaged by Rio Tinto to replace an existing 14-ton deaerator vessel that had failed. The deaerator plays a critical role in removing dissolved gases from boiler feedwater, protecting steam systems from corrosive damage.

Scope of Work

  • Demolition: Removed the existing deaerator vessel, including all associated welded pipework and grating.
  • Design and Engineering: Undertook the engineering and design of a new pipe network, which involved finite element analysis to ensure optimal performance and safety.
  • Off-Site Fabrication: Fabricated the required pipework off-site, ensuring quality and efficiency before installation.
  • Installation: Installed the new deaerator vessel along with the associated pipework, ensuring all components met the new design specifications.
  • Welding and Cladding: Conducted pressure welding of stainless carbon piping and provided cladding to protect the pipework.
  • Commissioning: Completed the commissioning of the new vessel, ensuring it operated effectively within the plant's steam systems.

Outcomes and Benefits

  • Timely Completion: Successfully completed the project within a tight schedule during the Cogen Outage plant shutdown, minimising downtime.
  • Quality Assurance: All welds were thoroughly inspected and met stringent quality requirements, ensuring the integrity of the installation.
  • Client Satisfaction: Delivered the project according to the client's design specifications, reinforcing Pructon's commitment to meeting client expectations and industry standards.
  • Enhanced System Performance: The new deaerator vessel effectively removes dissolved gases, improving the reliability and longevity of the steam systems.